Your new headquarters building is nearing completion. Construction on Northern Electric’s headquarters continues to be within the budget and on schedule. As of July 31, 2026, 41% of the $7.1 million budget has been expended. Interior work has progressed within the expected timeline and JDH Construction still expects the building to be ready by November 2026. As taping and texturing wraps up, the ceiling grid and overhead lights will be installed.
We will continue to provide highlights as the project continues. For more information about your new headquarters, please talk to your director or co-op manager.